Carleton wind farm: all 73 wind turbines erected

Innergex Renewable Energy Inc. (TSX: INE) (the "Corporation") announces that all 73 wind turbines of the Carleton wind farm have been erected. Access roads and the electrical sub-station have also been completed. The commissioning is underway and commercial operations should begin by November 30, 2008, as originally planned.

Innergex owns 38 % of the Carleton wind farm through its interest in Cartier Wind Energy. TransCanada Corporation holds 62 % ownership in the wind farm.

Construction of the project began in October 2007. The project has a total installed capacity of 109.5 megawatts (MW) and will generate 340,000 MW-hr of energy per year. Expected annual revenues for this wind farm should total $26 million.

Read more: Innergex Renewable Energy Inc ( INE )